Our Work Speaks for Itself
Every plant we design is engineered to solve a specific problem — compliance pressure, process water quality, energy costs, or waste. Here are some of our completed installations.
Industrial RO Plant — Pharmaceutical Unit
Challenge
High TDS borewell water (1800 mg/L) causing equipment scaling in API production.
Solution
2-pass Industrial RO with antiscalant dosing + DM polishing.
Outcome
Process water TDS reduced to <10 mg/L. Zero scaling incidents post-commissioning.
ZLD Effluent Treatment Plant — Textile Dyeing Unit
Challenge
TNPCB Red Category notice for non-compliant discharge. 8,000 mg/L TDS dyeing effluent.
Solution
Physico-chemical ETP + MBBR biological stage + RO + MEE Evaporator.
Outcome
100% ZLD achieved. TNPCB compliance certification obtained within 90 days.
Sewage Treatment Plant — Residential Apartment Complex
Challenge
CMDA mandatory STP compliance + recycled water for flushing & gardening.
Solution
MBBR STP with tertiary filtration + UV disinfection.
Outcome
Treated water reused for 100% flushing and landscaping. CMDA NOC obtained.
Packaged Drinking Water Plant — FMCG Manufacturer
Challenge
FSSAI compliance for in-house packaged water + supply chain cost reduction.
Solution
Multi-stage RO + UV + Ozone + SS 316 hygienic pipeline.
Outcome
BIS IS 14543 compliant. ₹8L/year savings vs. vendor-purchased water.
Biogas Plant — Food Processing Factory
Challenge
High organic waste disposal cost + fuel bills for boiler.
Solution
Anaerobic digester biogas plant with gas purification + boiler integration.
Outcome
Boiler fuel cost reduced by 40%. Waste disposal cost eliminated.
Solar Rooftop EPC — Manufacturing Plant
Challenge
Rising electricity bills (₹12/unit from TANGEDCO) cutting into margins.
Solution
Monocrystalline PERC panels + string inverters + net metering setup.
Outcome
₹9.5L annual savings. ROI achieved in 4.2 years.
ETP for Hotel & Resort — Backwater Discharge Compliance
Challenge
Coastal Zone Regulation (CRZ) strict compliance for effluent near backwaters.
Solution
Extended aeration STP + sand/carbon filtration + CRZ-compliant design.
Outcome
CRZ compliance achieved. Zero discharge into sensitive coastal zone.
DM Water Plant — Boiler Feed for Textile Mill
Challenge
High hardness boiler feed water causing scale, frequent boiler tube failures.
Solution
Dual-bed DM plant (cation + anion exchange resins) + degasser.
Outcome
Boiler feed TDS <1 mg/L. Zero tube failures in 18 months post-installation.
Have a similar challenge?
Let's engineer your solution.